Pavilion - February 2022

Construction continues to progress on site at Pavilion as the building’s form, designed by Selwyn Blackstone Architect establishes its street presence now that the structure is out of the ground.

The new year kicked off with concrete pours for the slabs on levels 3 and 4, with level 5 due to be completed in the coming weeks. Formwork has been stripped on the basement levels and up to level 2, with the concrete defecting process currently underway in these areas. Temporary amenities will be moving into the basement later this month, along with commencement of high-level services rough-in and wall framing.

Date February, 2022