Custom - March 2022

The tower crane dismantle has taken place on site at Custom Highett, along with the completion of sewer branch drain works. Roofing works are continuing to make progress, together with lightweight cladding and brickwork on the lower levels of the façade, flooring installation, internal wall and floor tiling, service hydraulic, electrical, mechanical, and wet fire fit off. With the tower crane dismantle complete the installation of the lift core and precast lid will commence, along with balustrade framing, internal framing and sheeting in the lobby and corridors, and joinery installation. 

Date March, 2022