Fitzroy Ltd - October 2020

The façade is coming along nicely at Fitzroy Ltd with all brickwork and metal cladding now complete to Level-4. External balustrades are also progressing well with works complete up to Level-7. Internally, plaster and painting has commenced on ground floor and Level-1 with Level-2 through to Level-4 to follow shortly after. In the basement, the structure for the car stacker is now complete with the electrical/ commissioning currently underway.