Fitzroy Ltd - October 2019

Demolition has already wrapped up on site and basement works have since commenced. Trucks have been running in and out this week in preparation for the piling rig due on site in the coming weeks. Next month will see piling, capping beam, bulk excavation, shotcrete and ground anchors as we make our way down to the bottom.

Date November, 2019
Related Projects
Share